Active street projects 

College Hills Boulevard: Loop 306 to Avenue N

Construction type: full-depth reclamation of roadway, drainage work, underground utilities, signalized intersection upgrades and ADA-compliant sidewalks and ramps.

Cost: $32.6 million.

Contractor: Reece Albert Inc.

Current status: 

  • Began May 2022.
  • Water and sewer utility replacement complete.
  • Project on track to be completed by the end of 2024.
    • Road construction is 80-85% complete.
    • The next big thing will be stabilizing the subgrade from Cumberland to Loop 306.

Howard Street: Glenna South to Sherwood Way

Construction type: mill and overlay, reconstruction of roadway, utility rehabilitation and installation of sidewalks/signal improvements.

Cost: $7.3 million.

Construction phase: Underway

Edmund/Glenna/29th Street

Construction type: mill and overlay, reconstruction of roadway, utility rehabilitation and installation of sidewalks/signal improvements.

Design phase: 100% complete.

Construction Phase: Utility work underway; road work will begin in November.

Ricks Drive Sidewalk

New sidewalk as part of a safe-routes-to-school project from Producer’s Park to Holiman Elementary School to Gordon Boulevard in the Paul Ann Subdivision. Construction is approximately 50% complete.

Road with street sign in the way saying Road Closed 

Street signage

Signs indicating what type of traffic is permitted.

  • Closed to thru traffic/no thru traffic – Normal traffic on the roadway is closed but vehicles are permitted to pass to access properties in the area.
  • Road closed – No vehicles beyond this sign or barricade.

*Please be mindful of speed limit reductions in construction zones.

Questions related to street projects or signage may be submitted using the question form on cosatx.us/streets.