Sunset Drive

Construction type: mill and overlay, full-depth reclamation of roadway, installation of sidewalks/signal improvements.

Estimated cost: $11.8 million.

  • Street portion: $4.75 million.
  • Utilities portion: $7 million.

Design phase: Design work in progress. 100% signed and sealed plans to be produced by Spring 2025.

Where: Loop 306 near Academy to Foster Road.

Christoval Road

Construction type: reconstruction of roadway, utility rehabilitation, drainage work, installation of pedestrian elements.

Estimated cost: $21 million.

Design phase: 100% complete. Construction timing contingent on identification of funding.

Where: Chadbourne to Ave. L.

Chadbourne St. (From Beauregard to Loop 306):

Plans are 95%. The project will be coordinated as part of the CACP Phase 1 Grant Program. Projected to bid in June 2025. This is a continuation and finalization of the Downtown Chadbourne Streetscape Improvement Project.

Down the road

  • Johnson Street. – In design
  • Avenue N. – In design
  • Main and 19th – Designing in-house
  • Ricks Drive – Designing in-house